The government has secured some of the cheapest financing available for big-ticket infrastructure projects, only to leave much of that money undrawn because Congress failed to provide sufficient counterpart funding in the national budget.
President Ferdinand R. Marcos Jr.’s economic managers, comprising the Cabinet-level Development Budget Coordination Committee (DBCC), have put numbers to the consequences. Over the past five years, an average ₱228.5 billion proposed for foreign-assisted projects (FAPs) under the National Expenditure Program (NEP) was slashed to ₱60.13 billion in the final General Appropriations Act (GAA). In 2024, Congress retained a mere 1.6 percent of the proposed allocation.
Manila Bulletin earlier reported that of 61 official development assistance (ODA) projects approved by the interagency Investment Coordination Committee (ICC), only 17 remained on schedule at end-2024. The other 44 suffered delays averaging up to 39 months.
Filipinos are therefore paying for the privilege of not using money already available for projects they badly need.
This matters when fiscal space is tight and government debt is elevated. In 2025 alone, the government obtained ₱351.3 billion in ODA for key infrastructure projects and priority programs.
The stakes go beyond accounting. Major transport infrastructure, including railways, can reduce commuting time, improve the movement of goods and workers, as well as lower business costs. The government’s infrastructure pipeline includes enormous undertakings such as the North-South Commuter Railway (NSCR) and Metro Manila Subway.
Worse, Congress’ cuts to FAP allocations have forced the government to resort to unprogrammed appropriations (UAs) for approved loan proceeds. The DBCC warns that, unlike ordinary UAs backed by excess revenues or new income sources, these claims have deficit implications and increase government borrowing.
As Congress deliberates on the record-high ₱7.2-trillion national budget for 2027, lawmakers must not repeat the budgeting failures that left approved FAPs starved of funds, years behind schedule, and accumulating fees for loans the country was unable to fully use.
Accountability for infrastructure does not end when a ribbon is cut. It begins when public money is budgeted.
*****